Production hall for Flottweg SE
From planning to production to assembly: C + P Industriebau Regensburg implemented a production hall for Flottweg SE in Vilsbiburg, Bavaria, from 2019 to 2020.
On the property, which was still undeveloped in 2018, with an area of approx. 55,000 square meters - which corresponds to approx. 8 soccer fields - is now "Plant 2" of the separation technology machine manufacturer. The almost 22,000 square meters production hall now stands on half of the area. For them, C + P delivered and installed steel constructions with a weight of approx. 1000 tons, lattice girders, crane runways and 3 aisles
The production of the truss took place with welding monitoring.
In order to ensure higher production capacities and an improved material flow, the client Flottweg SE invested around 40 million euros in the new "Plant 2".
Developer | Flottweg SE | |
Service | Structural Steelwork | |
Tonnage | 1000 t | |
Place of construction | Vilsbiburg, Bavaria |
CHRISTMANN + PFEIFER.
The ideal network of specialists for your building project.
Structural Steelwork.
Due to its sustainable characteristics, flexibility of use and economic efficiency, we rely on steel as the ideal material for industrial buildings.
Structural Steelwork Production.
Thanks to our own production sites in Germany, we can flexibly handle production capacities at any time and implement projects with pinpoint accuracy.
Sites.
Construction requires regional support, so CHRISTMANN + PFEIFER is represented via several branches and production facilities throughout Germany.